D78 Stock 'In Works' at Wakefield and at Ealing Common Depot
I am extremely grateful to Mike James of London Underground's Chief Engineer's Directorate for providing me with and allowing the reproduction of the photos that follow.
Mike is the Line Upgrade Engineer for London Underground, and is deeply involved with this project so what follows here is very much from the horses mouth!
The photos that appear initially are those that I feel are the most significant and benefit from being reproduced in as large a format as I can here and the remainder form new galleries with captions and explanations as appropriate.
This first selection was taken during July 2004 and are of Train 1.
Train 1 at Wakefield July 2004
General external view. As can be seen the exterior paint work has been attended to, but much internal attention is still ongoing.
The car end windows have been cut out and framed, and the Porter Buttons resited.
A considerable amount of corrosion was found, particularly in the cab areas, and of course this needed to be thoroughly addressed.
Similarly corrosion was found in the saloon door areas as seen here.
This is a 'door engine' - the device which opens and closes the doors. Note the new straps fitted to locate the device more securely. This should improve the reliability and performance of the doors.
The aperture cut into the rear of the DMC to house the GPS equipment associated to the Customer Information system.
This photo gives a superb impression of just how much work is involved in such a project. As you will note, there are no interior panels visible - the same will occur with every car that goes through the programme.
All new seating is being installed and is of a completely different style and construction to that previously fitted. The panelling seen here will protect the underseat areas.
|