![]() |
SCENIC LINE WORK REPORTS 27 February 2021 ('Click' on Photos to 'Enlarge') |
---|
27 February 2021 Crew: GaryM, KentS & DanielS
Cleora
Salida
Poncha Junction
Gunnison
Extra Board
24 February 2021 Crew: GaryM, GrantC & KentS
Salida
Gunnison
Extra Board
20 February 2021 Chow: GaryM, GrantC, TomG & KentS
Gorge
Cleora
Salida
Poncha Junction
Gunnison
Crested Butte
Extra Board
10 February 2021 Crew: GaryM, GrantC, DanielS, TomG & KentS
Cleora
Salida
Poncha Junction
Gunnison
Extra Board
6 February 2021 Crew: GaryM, GrantC, DanielS & KentS
Cleora
Gunnison
Extra Board
3 February 2021 Crew: GaryM, GrantC, DanielS, DanS, TomG & KentS
Gorge
Cleora
Salida
Gunnison
Extra Board
30 January 2021 Crew: GaryM, DanielS, DanS, TomG & KentS
Gorge
Cleora
Salida
Gunnison
23 January 2021 Crew: GaryM, GrantC & TomG
16 January 2021 Crew: GaryM, GrantC & TomG
Salida
Extra Board
13 January 2021 Crew: GaryM, GrantC, DanielS, DanS & TomG
Gorge
Salida
Mears Junction
Gunnison
Extra Board
10 January 2021 Crew: GaryM, GrantC, DanielS & TomG
Mears Junction
Extra Board
6 January 2021 Crew: GaryM, GrantC, KentS & TomG
Salida
Gunnison
Extra Board
DanielS added loose bricks in the kiln ruins.
GaryM started scenicing around the roundhouse, touched up ballast, added more dirt and some grass.
DanielS worked on laying out the farm and installed the barbed wire fencing.
KentS worked on track feeder hookups and tortoise installations.
GaryM glued dirt and ballast around the roundhouse foundation.
KentS continued working on track feeder hookups and tortoise installations. Below, is KentS new breaker panel under Gunnison.
20 February 2021 Crew: GaryM, GrantC, DanielS, DanS, TomG, StuJ & KentS
DanS painted the waterpipe 'shelf' rocks.
DanielS worked on the charcoal kiln ruins.
GaryM painted the sculptamold and added ballast around the roundhouse foundation.
StuJ brought out some corral fencing for the farm.
TomG stained the ties for the spur off the Baldwin branch.
StuJ completed some kits; a bank, saloon, and red light dtstrict shacks.
DanielS worked on the backdrop.
GaryM applied weathering powders to the roundhouse foundations, inspection pits, and turntable pit walls.
DanielS worked on the farm layout.
TomG laid subroadbed for the spur off the Baldwin branch.
DanielS touched up the ancient roadbed spur and the charcoal kiln bricks, and began working on the backdrop.
GaryM and KentS removed the main switch panel and cutout the new panels. GaryM also started working on laying out the trackplan on the panels.
DanS worked on the rock ledge for the water pipe.
DanielS touched up the charcoal kiln bricks and scenery.
GaryM applied washes to the DG roundhouse foundations.
KentS installed 5 new tortoise machines. TomG finished spiking in the Baldwin track.
DanS worked on the water pipe.
DanielS put in the charcoal kilns.
GaryM applied washes to the DG roundhouse foundations.
KentS assembled new switch machines. TomG worked on the Baldwin track.
16 January 2021 Chow: GaryM, GrantC & TomG
GaryM continued to lay down the DG roundhouse flooring over the ties and gaps to the foundations, on the
east stalls.
DanS worked on the water pipe scenery.
GaryM continued to lay down the DG roundhouse flooring over the ties and gaps to the foundations, completing the west side stalls, and the first two
east stalls.
DanielS worked fascia repair.
TomG installeled ties and spiked down connecting trackage.
10 January 2021 Chow: GaryM, GrantC, DanielS & TomG
DanielS worked fascia repair.
GaryM continued to lay down the DG roundhouse flooring over the ties and gaps to the foundations, completing the west side stalls, and the first two
east stalls.
TomG worked on the new trackage.