TrainWeb.org Facebook Page
Glastonbury
S&DJR Crest Somerset & Dorset Joint Railway
Signalling at Glastonbury
S&DJR Crest
Introduction Wells Branch Junction Early Signalling 1878 Changes 1901 Changes 1930 Changes BR Changes Block Working

Introduction

Glastonbury station was situated on the branch of the Somerset & Dorset Joint Railway (S&DJR) from Evercreech Junction to Highbridge in the county of Somerset. It was also the junction station for the S&DJR branch to Wells.

Glastonbury station was opened on 28-Aug-1854 as the terminus of the Somerset Central Railway (SCR), a broad-gauge (7' 0") line from a junction with the Bristol & Exeter Railway (B&ER) at Highbridge. Within four years work had begun on extending the line at both ends, with the westwards extension from Highbridge to Burnham opening on 3-May-1858 and the eastwards extension from Glastonbury to Wells a year later on 15-Mar-1859.

The SCR then began another extension from Glastonbury eastwards to Bruton, with the aim of meeting up with the northwards expansion of the Dorset Central Railway from Wimborne. This extension was constructed as standard gauge (4' 8"), with the existing SCR system becoming mixed gauge, and it was opened on 3-Feb-1862. Shortly afterwards the DCR and SCR amalgamated and on 1-Sep-1862 formed the Somerset and Dorset Railway (S&DR). The broad gauge fell into disuse and was removed from the S&DR system about 1870. The S&DR eventually became eventually the Somerset and Dorset Joint Railway.

At the eastern end of Glastonbury station there was a level-crossing over Dyehouse Lane and a hut was provided there for the gate-keeper. Further east between Glastonbury and the site of Wells Branch Junction were two more level-crossings, Paradise and Cemetary Lane - from contemporary recollections the latter had a ground frame-type hut complete with nameboard, but nothing else is known. A short distance to the west of the station lay Aqueduct Crossing, which is believed to have had a crossing-keeper but no signalling. Click here for a track plan of Glastonbury in 1904.


Wells Branch Junction

When the Bruton extension was constructed it diverged from the Wells extension about a mile north-east of Glastonbury, at a location known subsequently as Wells Branch Junction. However Glastonbury itself was the actual interchange station for the two lines, the trains to and from Wells and West Pennard (the first station eastwards on the Bruton extension) traversing the same single line as far as Wells Branch Junction. Naturally this remote junction had to be manned and the various references contained within the 1864 S&DR Rule Book give an interesting example of contemporary S&DR signalling practice.

The 1864 S&DR Rule Book stated:-

WELLS BRANCH JUNCTION

All trains approaching this Junction from Wells, or from West Pennard, are to stop fifty yards short of the Points. No Train, under any circumstances, must pass the Junction from either end, unless accompanied by the Pilotman appointed for that purpose, and who is distinguished by a broad red badge on the right arm.

When there are two Trains to pass over the Junction in the same direction, the Pilot must accompany the first Train on to the Junction, and, having despatched it, must wait for the second, and then proceed to Glastonbury. The second Train must not be passed over the Junction until the Pointsman in charge receives a telegram from Glastonbury that the first Train is in. The Pilotman will then accompany the Train over the Points and into Glastonbury, unless another Train is due at the Junction. He will in all cases accompany the last of such Trains to Glastonbury. The Trains from Glastonbury are to be worked over the Junction in the same manner.

Any departure from the Regulations will subject the offender to instant dismissal, and will render him liable to prosecution for having either wilfully or carelessly obstructed the working of the Line.

When two Trains arrive at the Junction at the same time, precedence in all cases is to be given to the Wells Branch Trains, and to Passenger Trains over Goods Trains.

A subsequent amendment stated that these rules would be "suspended until further notice" with effect from 8-Apr-1867, after which "All Trains must be worked over this Section of the Line on the Block System of Telegraphing, and in strict accordance with the Instructions contained in Section 3, page 19, of the Company’s Book of Rules and Regulations". The precedence for trains at Wells Branch Junction remained as before. A later notice read as follows:-

WELLS JUNCTION & GLASTONBURY

---------

The following Special Regulations for crossing Trains out of their ordinary course are applicable to the Wells Branch Junction and Glastonbury ONLY.

---------

When TRAINS MARKED in the Working Time Book TO CROSS AT THE JUNCTION ARE REQUIRED TO CROSS at GLASTONBURY, the following Rules are to be observed, viz:-

Glastonbury will give SIX distinct strokes of the Bell, which are to be REPEATED by the Signalman at the Junction, who must AFTERWARDS obtain "LINE CLEAR" in the USUAL MANNER, and then send on the Train into Glastonbury giving to the Driver a signed order to proceed on the form supplied for that purpose, which shall be his authority for proceeding accordingly.

When TRAINS MARKED in the Working Time Book TO CROSS AT GLASTONBURY, ARE REQUIRED TO CROSS AT THE JUNCTION, the following Rules are to be observed, viz:-

Glastonbury will give TEN distinct strokes of the Bell, which are to be REPEATED by the Signalman at the Junction. Glastonbury must AFTERWARDS obtain "LINE CLEAR" in the USUAL MANNER, and then send on the Train to cross there; giving the Driver a signed order to proceed on the form supplied for that purpose, which shall be his authority for proceeding accordingly.

It is evident from these instructions that Wells Branch Junction had a signalman and presumably some form of shelter would have been provided for him and the equipment at that isolated place. However whether any form of proper signal-box (SB) with an interlocked lever-frame existed, and what signals might have been provided (if any), is unknown. The S&DJR Officers’ Minutes for 8-Nov-1876 (PRO file RAIL 626/16) record a decision for "Wells Junction, Glastonbury to be interlocked" at a cost of 250, but at a subsequent meeting on 9-Mar-1877 it was decided that the "resignalling of Wells Branch Junction near Glastonbury" (apparently now at a cost of 190) was to be deferred. In view of its subsequent demise it is unlikely that in fact any work was done.


Early Layout

At Glastonbury itself the early history is very vague and apart from the material about Wells Branch Junction there appear to be very few references to the signalling prior to 1878. The earliest known record is a copy in PRO file MT6/11/91 of a B&ER "Instructions to Head Guards and all others concerned in the working of the single line between Glastonbury and Highbridge" dated 16-Sep-1854. The gist of these instructions is that no train was to move over the line without the guard (who was nominated specifically on a daily basis) on board, the implications being that the whole branch at that time was worked as a single section with a form of ‘Pilot Guard’ working.

The S&DJR Officers’ Minutes for 8-Nov-1876 also contain an entry about Glastonbury, stating that "a signal-box to be provided at the north end of the Glastonbury goods yard...points to the goods yard and north end of the loop to be worked from it...present signals to be removed and new signals provided...points at the south end of the loop to be bolt-locked from the new box and worked from the ground box as at present. Block to terminate at the box at either end of the station...bell and gong communication to be provided". The estimated cost was 680. It is not known what the ‘ground box’ was, nor whether the ‘new box’ replaced any other existing signal-box. The reference to the block ’terminate...at either end of the station’ is also confusing. However some work did indeed take place and a new signal-box (SB) opened in 1878.


1878 Alterations

In 1878 the layout at Glastonbury was re-organised with the construction of an additional line alongside the existing track from the station to Wells Branch Junction, which was abolished on 7-Dec-1878. After that date the Wells and Evercreech Junction branches had independent tracks east of Glastonbury, without any physical connection at their divergence at the site of the former Wells Branch Junction. The Down platform became an island, with its northern face served by a loop that acted as a bay platform for the Wells trains.

Glastonbury signal diagram 1878
Glastonbury Signal Diagram 1878
Click diagram for larger image

A new SB was constructed at the Highbridge (north) end of the Up platform and this contained a 22-lever frame (19 working and 3 spares). The work was inspected by Major Marindin and his Inspection Report dated 16-Dec-1878 can be found in PRO MT6/218/10, which includes the signal diagram shown above. In his Report the Major requested the provision of a trap-point and disc signal at the end of the ‘Wells loop’; it is not known when these were provided nor what alterations were made to the frame to accommodate these, but one must assume that the diagram represents an arrangement that did not exist unchanged for very long.

Glastonbury old signal-boxA mystery surrounds the new SB that was opened at Glastonbury as part of the 1878 alterations. There is an old photograph of the front of the SB, probably taken in the 1890s, which shows the box as a S&DJR TYPE 2 design, but unusually the timber superstructure had outside framing and extended lower down at the front than normal. It is possible that the SB had less stone or brick in its construction than others of its type because of ground loading problems - certainly most buildings at the station were of timber (although the nearby former S&DJR offices were brick).

A distant view of the rear and station end of the SB can be seen in a photograph of the station from the collection of the late Robin Atthill, which appears on page 101 of the OPC "An Historical Survey of the Somerset & Dorset Railway", and it would appear that at least there was a brick chimney stack at the rear. In the absence of any other evidence, it must be assumed that the SB illustrated in those photographs was the one erected in 1878, which would make it the first of its Type - this is curious, because it would have been erected towards the end of a period (1876-9) of building Type 1 SBs, and no other Type 2 SBs are known to have been erected before the mid-1880s.


1901 Alterations

Glastonbury new signal-boxIn 1901 further changes took place at Glastonbury and on 3rd June that year a new SB was opened adjacent to the earlier box. The new SB contained a 27-lever Stevens-pattern 4.1/8"-centres interlocking frame and was built to the S&DJR TYPE 3 design with a hip roof, although curiously again it was one of the few constructed entirely of timber - which reinforces the suspicions about ground loading. The SB seems to have been rather longer than was necessary for the size of lever-frame, but one can only speculate whether this implies some unknown plan for future expansion or merely the convenient use of ‘standard’ panel sizes.

Glastonbury signal diagram 1901
Glastonbury Signal Diagram 1901
Click diagram for larger image

The new works were inspected by Major Pringle and his Inspection Report of 30-Dec-1901 can be found in PRO MT6/1097/5 together with the signal diagram shown above. Two items worthy of note here are the provision on points 9 and 15 of ‘Blacks Locks’, which were a form of ‘economic’ FPL widely used by the London & South Western Railway, and the existence of a 'safety bar' 21 on the main line to the east of the level-crossing gates. This bar served a ‘route holding’ function while an Up train traversed the distance from signal 26 to the commencement of the lock bar worked by FPL 18; it was removed at some unknown date after 1930 and lever 21 was spare thereafter.

Major Pringle refers in his Report to the provision of the new SB with 27 levers (including 3 ‘push-pull’), 2 new ‘draw ahead’ signals (assumed to be 7 and 8, although it is not known when 3 PUSH was provided), and catch points on the "dead-end siding" at the end of the Wells loop (presumably 9). However he called for the provision of "entrance discs" for points 13 and 14 and also for the points discs to be worked from the SB. This work involved the extension of the frame by a further two levers, and apparently also the conversion of an existing lever to ‘push-pull’ working, as in his further Inspection report dated 24-July-1902 he records the frame as being then of 29 levers including 6 push-pull. Unfortunately no diagram exists to show the revised layout, but from later information it would appear that the frame extension was carried out by adding one extra lever at each end.


1930s Alterations

Sadly there is a very limited coverage of Glastonbury in surviving S&DJR Signal Instructions, the first one being SI 186 which records that on 3-Nov-1905 the ground signal reading from the Down Siding to the Down Loop was to be moved into the ‘six foot’ - this presumably was the signal adjacent to points 14 that originally was a ‘point disc’ in the 1901 diagram. However it is fortunate that a copy survives of SI 300, as this records the details of a series of significant changes which occurred at Glastonbury in 1929. On 27-Dec-1929 the Down Distant was moved about 428 yards nearer to Ashcott, whilst the next day saw the following alterations:-

Glastonbury signal diagram 1930
Glastonbury Signal Diagram 1930
Click diagram for larger image

The results of all those changes can be seen in the signal diagram shown above, which is taken from a S&DJR copy stamped 27-Feb-1930. Comparison with the 1901 diagram will show the addition of levers A and 28 (believed to have happend in 1902), and also that there have been some other minor alterations at some time (eg the abolition of the Black's Lock on points 16 and the addition of ground signal 22 PULL), but dates for these changes are unknown. After the 1929 changes ground signals 7 PULL and 8 PUSH both became "running shunts" - in other words they had to be pulled ‘off’ before the Down Home signal 1 could be cleared for running movements along the Down Main. SI 300 stated that the relocated Down Home was now 1000 yards from the Down Distant, but this may have been only an approximate intention, as distances given in the 1930 diagram are taken from the S&DJR original and are believed to be correct.

Down Main Starting co-acting signals and subsidiary armThere was a further minor change on 20-Dec-1931 (SI 319) when two ground signals (apparently 20 PUSH and 27 from the descriptions given) were each moved 5 yards further from the SB. Then on 10-June-1934 (SI 350) the Down Starting signal (3 PULL) was provided with a new post 34’ high, still with 2 co-acting arms, and at the same time the Shunt Ahead arm (3 PUSH) was relocated further down the post below the lower co-acting arm. It was probably at this time that the original wooden post was replaced by the later lattice post and the revised signal configuration (see picture) provides a useful reference for dating the many photographs taken at that end of the station.

The gates at Dyehouse Lane level-crossing were worked by hand by a crossing-keeper and it is believed that lever 19 in the SB worked directly on the Gate Locks. A plan from the British Railways period marks a ‘wickets lever’ ground-frame outside the hut, but the actual signal diagram circa-1960 (more about this here) mentions levers in the hut working the Gate Stops and the Wickets.


BR Period Alterations

Official records become very scarce again after the early-1930s but it is believed that the overall arrangement continued unchanged, with the possible exception of the removal of the safety bar 21 as mentioned above. Ground signal 20 PULL was abolished on 31-Dec-1949, its function being combined with signal 27.

The next substantial change came on 29-Oct-1951 with the complete closure of the Wells Branch. As a result signals 4, 5, 23 and the ‘from Wells’ fixed distant were removed, as were ground signal 20 PUSH and trap points 9. The ‘Wells Loop’ end of crossover 16 was retained as a trap-point along with signal 22 PULL, but FPL 15 was removed. It is unclear exactly how soon these changes took place, as the branch itself was not lifted until some time afterward formal closure.

Interior of Glastonbury signal-box circa-1962
Inside Glastonbury signal-box looking from left to right Inside Glastonbury signal-box looking from right to left Diagram hung in Glastonbury signal-box Inside Glastonbury signal-box looking at the rear wall
Looking from left to right Looking from right to left Signal Diagram View of the back wall
Click on the thumbnail images to see larger pictures

Information for the 1960s period comes from some photographs taken inside Glastonbury SB circa-1962 by David Milton. The SB diagram at that time was of British Railways (Western Region) origin and the master copy was dated Feb 1959, but it is not known what change had prompted BR(WR) to produce a new diagram at that time. (That diagram actually contained an error - lever 1 is marked correctly as working the Down Home, but it is listed also as being a 'space' ! The photographs of the lever-frame confirm that lever 1 was still in use.) A diagram for the signalling circa-1960 is shown below, and apart from the main changes brought about by closure of the Wells Branch there have been some further alterations.

Glastonbury signal diagram circa-1960
Glastonbury Signal Diagram circa-1960
Click diagram for larger image

In particular it should be noted that lever 3 has been converted to ‘normal’ working of the Up Starting signals only, with the subsidiary 'Shunt Ahead' arm now worked by lever 4 (although the box diagram actually showed - incorrectly - that arm as still located between the two co-acting main arms). A track circuit ‘A’ has been added at the eastern end of the loop and signal 27 has been converted to a ‘yellow’ ground signal, but curiously signal 6 PUSH has reverted to being an ordinary (red) ground signal. [NOTE: There is some doubt about these ground signal changes - whilst the former is likely (although no photographic evidence has come to light yet), there seems little reason for the latter and there are some photographs from about the same period which suggest that it was not changed.]

It is not known if any further changes occurred to the signalling installation in the last few years before closure of the signal-box on 6-Mar-1966 along with the rest of the line.


Block Working

There are difficulties in establishing the limits of early S&DJR block sections, because of the practice of providing block telegraph instruments at intermediate stations. This problem affects research into Glastonbury also, because of the uncertain status of Ashcott at that time. A decision was made at the S&DJR Officers’ meeting on 8-Nov-1876 to provide a block switch at Ashcott, but unlike similar stations (eg Midford, Henstridge) at that time there is nothing about it in WTT Appendix No 7 dated 1-Mar-1886, which is the next available record.

An S&DJR letter dated 16-Dec-1878 states that the block working at Glastonbury was by "train staff and ticket with Absolute Block", although it is only an assumption that this was intended to refer to all three sections (ie to Shapwick, West Pennard and Wells). However it would appear that in fact this was a false claim, as at that time the S&DJR was working its single-lines by block telegraph only. This is borne out by evidence in PRO MT6/609/1, where the S&DJR’s entry in the "Returns on systems of control as at 31-Dec-1885" under the Railway Regulation Act 1873, which states "Burnham - Evercreech 23m 69c single...worked on the Absolute Block system (in addition to the Train Staff system on single line sections)", has a hand-written note appended saying "this appears to be an incorrect return, this Company do not use the Train Staff with their trains but only with their Banking Engines" and there is a subsequent S&DJR letter dated 12-Apr-1886 apologising for their inaccurate return.

In Working Time Table (WTT) Appendix 7 dated 1-Mar-1886 the Wells-Glastonbury section is one of only two block sections specifically listed as being worked under "Train Staff and Ticket" regulations. However later that year the widespread introduction of Electric Train Tablet (ETT) working on the main Bath to Wimborne line was accompanied by the provision of Train Staff and Ticket (TS&T) working on the whole of the Evercreech Junction to Highbridge branch. The details are given in WTT Appendix 8, where the sections either side of Glastonbury are listed as extending to West Pennard, Shapwick and Wells. TS&T working was replaced in due course by ETT working to West Pennard in 1888 (using Tyers No 1 instruments), Shapwick in 1891 (Tyers No 3) and Wells ‘A’ in 1895 (Tyers No 1).

BR(WR) Electric Key tokens used at GlastonburyAbout 1951-53 the ETT working on the Evercreech Junction to Highbridge branch was replaced by the Western Region pattern of Electric Key Token (EKT), but the Wells Branch is believed to have remained worked by Tyers No 1 ETT until closure. EKT working from Glastonbury to West Pennard was introduced on 6-Apr-1952, using ‘B’ configuration tokens. EKT working to Shapwick used ‘C’ configuration tokens, but the date of introduction is unknown. This arrangement continued until the closure of West Pennard SB on 14-Aug-1964, after which the section became Evercreech Junction North - Glastonbury re-using the ‘B’ configuration tokens, and this revised situation continued until the complete closure of the line on 6-Mar-1966.

© CJL Osment 2004-16
Thanks to David Milton for access to his photographs, to Steve Erlicher and Peter Kay for material from the Public Records Office, and to Christopher Hill of the LNWR Society and John Wakeman for assistance with producing the diagram images.
Signal-box interior photographs © David Milton. Old signal-box photograph courtesy Maurice Shaw. New signal-box exterior photograph, track plan and WTT Appendix extracts courtesy S&DRT Archives. Other photographs from WCRA collection.


References

Introduction Wells Branch Junction Early Signalling 1878 Changes 1901 Changes 1930 Changes BR Changes Block Working